Posted by on April 12, 19103 at 09:34:43:
DANILO Y. REAL
No. 4 Baltazar St./5th Avenue
Caloocan City, M. Manila 1400
Philippines
Tel. (00632) 365-7584 & 365-7586
Mobile: (0063) 9164316390
Email: danilo_marina@yahoo.com
Job Objective
Civil Engineer/Project Engineer -Consultant/Inspector, Estimator/Quantity Surveyor.
Qualifications
Licensed and Registered Professional Engineer in the Philippines.
Over 15 years experience both office works and project supervision of heavy architectural-civil and industrial constructions.
Graduated BSCE, October 1978, Feati University, Manila Philippines.
PC literate on MSWORD, EXCEL, MSPROJECT
Experience:
1993 TO 2003
Project Engineer/Consultant
Saudi Electricity Company (SEC CENTRAL)
Civil Projects Division
P.O. Box 57, Riyadh 11411
Saudi Arabia
Tel. (009661) 403-2222 Ext. 2934
Supervision of the company’s ongoing projects being undertaken by various contractors. Ensuring that these projects are completed to the highest standards in accordance with the contract documents (Contracts, Plans, and Specifications).Includes progress monitoring of various projects, checking quality of materials and. craftsmanship, and the adoption by contractors of appropriate safety standards. Inspections are carried out to check all is according to approved materials, as per specifications, and as per approved drawings. Assists with projects in identifying and evaluating problems arising, suggesting solutions and recommending suitable corrective measures. Requires contractor to conduct periodic tests on concrete, masonry, rebars, soils and asphalt, etc. Conduct bi-weekly meeting with the contractor to review progress and sort out problems arising. Review and approved submitted sample materials, catalogs and brochures, as built drawings, and monthly progress billings. Conduct punch listings before preliminary handover of the project.
Projects undertaken: (2001 – 2003)
400 nos. Transmission Towers, 132kV Overhead Line Section (180km) from SS8065 – 8070 to 8077, Riyadh to Quayiyah
Projects undertaken: (1999 – 2001)
450MW Gas Turbine Electric Power Plant - Onaiza, Qassim
Complete construction and erection of the following buildings – Turbine (for 6 nos. x 75MW Gas Turbines), mechanical workshop, electric workshop, fuel handling fuel pump house, 3 nos. fuel management, central control, fire fighting, 3 nos. local controls, 3 nos. battery, chilled water service (for 6 nos. x 3600 HP pumps. Construction of open shade steel structures for 3 nos. x 200MVA x 12.5kV to 132kV step-up transformers, 2 nos. 230MVA x 132KV to 4.16kVservice transformer (for chilled water system), 6 nos. 2.60mVa x 4.16kV to 480Vauxiliary transformer, 2 nos. 1mVa x 4.16kV to 480V diesel auxiliary transformers, 6 nos. x 1.25mVa x 13.8kV to 480V crude oil auxiliary transformers, water wash, and fuel unloading station.
Complete construction of 3 nos. x 40,000m3 crude oil tanks, 1 no. x 40,000m3, RC ice storage tank (30,000m3 cap.).
Other construction such as RC U/G trenches for fuel lines, cable lines, water, and fire fighting, asphalt roads, security fences, hardscaping and landscaping.
Projects undertaken: (1998 – 1999)
Three (3) nos. Substation Builldings rated 132kV/2x100mVa in Onaiza, Qassim (SS8824, 8825, 8826)
23 nos. Transmission Towers, 132kV Overhead Line Section IV (6km) from SS8818 – 8800 to 8801, East Buraida, Qassim
50 nos. Transmission Towers, 132kV Overhead LIne Section V-I (20km) from SS8824 – 8801, Onaiza to Qassim Power Plant, Qassim
133 nos. Transmission Towers, 132kV Overhead Line Section V-II (40km) from SS8824 – 8802 to 8803, Onaiza to Al Kabra, Qassim
Projects undertaken: (1996- 1998)
One (1) Substation Building rated 132KV/13.8KV/180MVA in Riyadh
99 nos. Transmission Towers, 380 KV Overhead lines from Power Plant no. 9 to Riyadh City
107 nos. Transmission Towers, 132KV Overhead lines from Power Plant no. 9 to Riyadh City
163 nos. Transmission Towers, 380KV Overhead lines from Power Plant no. 9 to Riyadh Industrial area.
Projects undertaken: (1994-1996)
One (1) Substation Building rated 132KV/120MVA in Riyadh
Three (3) Substation buildings rated 33KV/60MVA in Qassim
Two (2) Substation Building rated 33Kv/40MVA in Qassim
Projects undertaken: (1993-1994)
One (1) Substation Building rated 132KV/100MVA in Al Kharj
Four (4) Substation Buildings rated 33KV/40MVA in Al Kharj
184 nos. Transmission Towers, 132KV Overhead Lines in Al Kharj
1992 TO 1993
Quality Control Engineer
Hyundai Engineering & Construction Co. Ltd.
P.O. Box 57909, Riyadh 11584
Saudi Arabia
Project : King Fahad Medical City
(Biggest Hospital in the Middle east)
Riyadh, Saudi Arabia
Supervision over subcontractors and inspection on various works according to approved plans and specifications. Activities pertaining to concrete works, precast concrete erection, structural steel erection, waterproofing, doors and windows, various architectural finishes (marble, ceramic tiles, acoustic ceilings, drywall, painting, etc.), hardscaping and hardscaping. Assists in identifying and evaluating quality problems, suggesting solutions and recommending corrective measures.
Conduct various tests for concrete, rebars, soil compaction, and asphalt tests. Liase with the Consultants and seeks approval for pre-concrete pouring, pre-installation inspections, and acceptance of other completed works. Prepares daily technical, progress reports.
1990 TO 1992
Quantity Surveyor-Estimator
Al Saad Contracting & Trading Co.
P.O. Box 13028, Jeddah 21393
Saudi Arabia
Preparation of Bill of Quantities and Cost Estimating as per clients drawings and specifications. Most of the works involves civil and heavy architectural works for residential palaces of Saudi Princes, Princesses, and Sheiks. Quantity Take-offs from site work, earthwork, concreting, heavy finishes like marble, decorative hard woods, architectural gypsum finishes decorative doors and windows, skylights, etc. Price sourcing/canvassing on local market, Europe, and USA. Liase with the consultant for clarifications.
1988 TO 1989
Civil Site Engineer
RMC Co. Ltd.
P.O. Box 16191, Riyadh 11464
Saudi Arabia
Project: Harpoon Missile Maintenance Facility
MODA Military Army Base, Al Kharj
Saudi Arabia
Consultant: US Navy
Project supervision on construction of RC Main Building, Ready Magazine Building. Installation of two (2) U/G fuel tank 12,000 gals. cap. ea., two (2) Genset 1 KW rating ea., three(3) Overhead Electric Cranes 5 tons cap. ea., roof ventilators and exhaust system. Painting and other finishing works. Other activities like quantity take-off, misc. survey layouts, preparation of construction schedules, manpower and equipment distribution, preparation of daily progress report and monthly progress billings. Liase with the Consultants and seeks approval of materials and inspection approvals to pre-concreting and other phases of activities. Project was built with American Codes, US Army, and US Navy specs.
1979 TO 1988
Civil Engineer (various positions held)
(Site Engineer, Quantity Surveyor/Estimator, Junior Design engineer)
Atlantic, Gulf & Pacific Co., Inc.
Makati, Metro Manila
Philippines
Generally involves project supervision, preparation of construction schedules-CPM Time Bar/Bar Chart, progress reports, liase with consultants. Quality Control Engineer over subcontractors, do quantity take-offs and costs estimates, preparation of price variation orders, and being also a project coordinator. Minimal structural design calculations and miscellaneous detailing of reinforced concrete and structural steel structures.
Held the following assignments:
Civil-Architectural-Structural Quantity/Cost estimator for International Bidding
Head Office, Engineering & Estimating Department
Makati, Metro Manila
Philippines
1987 - 1988
Civil Site Engineer
Pacific Star Building (32- Story High
Construction of structureal steel-framed building combined with reinforced concrete and all architectural finishing work.
Makati, Metro Manila
Philippines
1985 - 1987
Civil Site Engineer
US Airmen’s Dormitory Building
Construction of three (3) nos. reinforced concrete buildings (3 storeys ea.) including all architectural finishing works and electro-mechanical works.
Clark Air Base, Philippines
1984 - 1985
Civil Site Engineer
Mina Al Ahmadi Oil Refinery Project
For Kuwait National Petroleum Co.
Japan Gas Corporation (JGC)
Construction of a new refinery. Supervision on erec
ction of various heavy to light structural steel frames and piping racks for heavy equipments and machineries, and process pipes from 4” to 36”.
Fahaheel, Kuwait
1983 - 1984
Civil Site Engineer
Balongbong Mini-Hydro electric Power Plant
Construction of a mini-dam, 1.8km steel lined U/G headrace, concrete lined forebay for water reservoir, 1.6km steel penstock 30” including RC trustblocks running downhill towards the Power Plant. RC power plant building including two (2) nos. 1.8KW turbines, overhead travelling crane, 1no. Substation, architectural finishes and other equipment.
Bato, Catanduanes Island
Philippines
1982 - 1983
Civil Site Engineer
Island Cement
Antipolo, Rizal
Philippines
1981 - 1982
Civil Site Engineer
Shell Oil Refinery Expansion
Tabangao, Batangas
Philippines
1980 - 1981
Junior Structural Design Engineer
Head Office, Engineering & Estimating
Makati, Metro Manila
Philippines
1979 - 1980
SEMINARS
Other Qualifications
Supervisory Training Program
Atlantic, Gulf & Pacific Co.
Makati, Metro Manila
Philippines
December 1985 (50 Hours)
Technical Writing Program
Atlantic, Gulf & Pacific Co.
Makati, Metro Manila
Philippines
July 1985 (36 Hours
Computer Concepts
Technology & Livelihood Center
Makati, Metro Manila
Philippines
March 1988
Programming Fundamentals (Pseudo Coding)
Technology & Livelihood Center
Makati, Metro Manila
April 1988